JRO2 Build
11/16 - Installed the pier plate and adapter for my mount
11/12 - Foam tile floor installed
11/8 - Finished stair railings
11/7 - Electrical secured
11/5 - Power washed and looking proud, back into an XL-5
11/4 - Started moving back in, completed electrical and LAN rough in, started installing Trex railings -2/3 complete
11/3 - Pod Moved, dome installed
10/31 - Begin POD move to new deck. 1/2 done!
10/28 - Moving contents of JRO into boxes so I can move the POD to the new deck
10/26 - Deck complete, ready for POD
10/25 - Stained stairs, almost the right color
10/17 - Finished installing posts & installed trim around deck
10/16 - Moved the pad and started making the stairs. Cut all holes in decking for posts. Started installing posts.
9/23 - 9/24 Posts and Decking installed. (despite me tumbling off the deck on the 3rd board!)
9/22 - Posts set, beams installed, framing installed, blocking installed (a good day) Ready for Decking!
9/21 - Stone arrived and I spread it all out. Took apart the old roll-off structure, reusing the beams for the new deck.
9/18 - Covered up with weed block, ready for 7 tons of 3/4" stone
9/17 - electrical and lan roughed in, trench backfilled before the rain
9/15 - 9/16 mixed and poured about 40 x 80lb bags of quickcrete. Footings, Pier and Pad are all done. Done with concrete work!
9/13 - STILL Stalled from rain! Hoping for a better weekend.
9/8 - Stalled for rain
9/7 - Holes made, materials arrived, ready for concrete -covered up due to rain
9/2 - Marked out for QuickTubes, ready to make holes! I have all the materials for building the new 12x12 deck coming Friday so it will be interesting to see how long this takes me to do. I hope to do all the concrete work this weekend, weather permitting.
JRO2 is the name of my SkyShedPOD XL-5 as it moved to a new nearby deck.
This page illustrates the build and move